Submit your Bakersfield plan check submittal through the City of Bakersfield e-Permit and Plan Review Portal, which runs on the ProjectDox platform. Before you upload anything, pull the correct submittal checklist for your permit type and format every plan sheet as a single-sheet PDF with a compliant filename. Skip either step and staff will bounce your package back during prescreen. If your permit type isn't listed in the portal yet, call the Development Center before you try to force a workaround.
TL;DR:
- Submittals must be uploaded as single-sheet PDFs with correctly formatted filenames starting with numbers to ensure proper sorting in ProjectDox, avoiding delays.
- The permit application requires specific documents such as full plans, structural calculations, soils reports, and energy compliance forms, which vary by project type.
- Completing the fee payment after uploading documents is essential, as review does not proceed until fees are settled through Click2Gov.
- The typical review for small solar permits can take 1 to 3 days, but more complex residential projects usually require several weeks, with delays often caused by resubmittal issues.
- Using organized, complete, and reviewer-ready structural reports, like those generated by ShearWise Pro, can significantly reduce correction cycles and speed up approval.
Table of Contents
- Where To Submit Your Bakersfield Plan Check Submittal
- What Documents Do You Need Before You Submit?
- What Are the File Format Rules for ProjectDox?
- How Do You Complete the Submittal Workflow Step by Step?
- How Long Does Plan Review Take, and What Slows It Down?
- Practitioner Tips to Cut Correction Cycles
- Why Organized Electronic Submittals Actually Change the Outcome
- A Faster Path to Permit-Ready Shear Wall Calculations
- Official Bakersfield Resources to Bookmark
- Sources
- FAQ
Where To Submit Your Bakersfield Plan Check Submittal
The city's electronic system is the front door for nearly every permit type now. You create an account, select your service, and work through the process without setting foot in a government building.
That said, the portal is still expanding, and not every permit category has made the jump to fully digital intake. The e-Permit and Plan Review Portal itself notes that some permit types remain unavailable online while the paperless rollout continues, so check the portal first before assuming a paper route is required.
Here's how to reach the right people and channels:
- Primary portal: bakersfield-ca-us.avolvecloud.com, the Avolve-powered ProjectDox system for building, planning, fire, water, and public works submittals.
- Development Center: the general contact point for submittal questions, reachable at DevBld@BakersfieldCity.us or 661-326-3720.
- Building Division: your fallback if a permit type isn't showing in the portal, or if you need clarification on which checklist applies to your project.
- In-person or paper submittals: still accepted in specific circumstances the city defines, mainly for permit types not yet digitized. Confirm with the Development Center before printing a full plan set.
Don't guess on this. A five-minute call to the Building Division can save you a week of resubmittal cycles if you're submitting a permit type the portal doesn't yet support electronically.
What Documents Do You Need Before You Submit?
Every submittal checklist on the Electronic Planning Application Submittal Process page is organized around two steps: prepare to submit, then submit. Skipping the "prepare" step is where most applicants lose time.
Pull the checklist that matches your specific permit type before you start uploading. A tenant improvement, a new single-family residence, and a solar installation each carry different document requirements, and the city publishes separate bulletins for many of them.
- Permit application form, filled out completely with the correct project address and scope description.
- Full plan set, including architectural, structural, and site plans specific to your project scope.
- Structural calculations, covering framing, lateral design, and any engineered components.
- Soils report, when the project scope or site conditions require it.
- Energy compliance documentation (Title 24 forms for California projects).
- MEP drawings for mechanical, electrical, and plumbing scope where applicable.
- Site plan, showing setbacks, easements, and existing structures.
Special cases have their own paths. A small solar PV installation, for example, follows an expedited submittal bulletin with a shorter, more specific list of required items. Look for downloadable templates on the city site rather than assembling your package from memory of a past project. Requirements shift, and an outdated checklist is a common cause of an avoidable rejection.
What Are the File Format Rules for ProjectDox?

ProjectDox handles overlay comparisons and version tracking by treating each plan sheet as its own file. Upload a multi-sheet PDF instead of individual sheets, and the system can't swap a single corrected page without forcing a full resubmission of the entire set. That single technical detail causes more delay than almost anything else in the process.
The city's naming convention guidance lays out the rules plainly:
- Plan sheets go in as single-sheet PDFs, typically sized 24x36, one sheet per file.
- Supporting reports (structural calcs, soils reports) can stay as multi-page PDFs.
- Filenames must start with a numeric sequence so documents sort correctly inside ProjectDox.
- Keep filenames under the character limit and avoid special characters like ampersands or slashes.
- Use revision suffixes such as
.1or.2when you resubmit a corrected sheet.
Pro Tip: Run a quick preflight before you upload: confirm each plan sheet PDF opens at the correct scale, that any scanned text is still searchable, and that sheet size matches 24x36. A sheet that looks fine on your screen but was scanned at the wrong scale is a classic cause of a prescreen kickback, and it's an easy thing to catch before submission rather than after.
How Do You Complete the Submittal Workflow Step by Step?
The workflow moves through the portal and ProjectDox in a specific order, and missing a step, like forgetting to pay fees before expecting review to start, stalls your project without you realizing it.
- Create an account on the e-Permit portal and select the correct application service and request type for your project.
- Name your project clearly using the address or a recognizable project identifier, then accept the terms of service.
- Upload your documents to the designated files folder, following the single-sheet PDF and filename rules covered above.
- Watch your email for upload and submit confirmation messages. No confirmation means something didn't go through.
- Wait for prescreen review. City staff check your package for completeness and determine applicable fees.
- Pay fees through Click2Gov, the city's payment system, once staff calculate the amount owed.
- Return to ProjectDox after payment to complete your formal submission into the plan review queue.
- Check ProjectDox regularly for prescreen or plan-check comments, and respond directly inside the platform rather than through separate emails.
Each step gates the next one. A submittal that sits unpaid in Click2Gov doesn't move into active review no matter how complete your plan set is.
How Long Does Plan Review Take, and What Slows It Down?
Timelines vary by permit complexity, and the city publishes different expectations depending on scope. A straightforward small solar PV permit that meets expedited criteria can move through review in as little as 1 to 3 days. A standard residential plan check with structural and MEP components typically runs longer, often several weeks, depending on reviewer workload and correction cycles.
The single biggest driver of delay isn't reviewer backlog. It's resubmittal. A package rejected at prescreen for a missing checklist item or a malformed PDF goes back to the end of the line, adding days or weeks that a five-minute file check would have avoided.
Common causes of delay include:
- Missing items from the permit-specific submittal checklist.
- Multi-sheet PDFs uploaded where single-sheet files were required.
- Incomplete or unsigned structural calculations.
- Filenames that don't follow the numeric-leading convention, causing ProjectDox to display sheets out of order.
- Fees left unpaid in Click2Gov, which stalls the handoff into active plan review.
Practitioner Tips to Cut Correction Cycles
Engineers and designers who submit frequently in Bakersfield tend to develop the same habits, because the ones who don't spend a lot more time in resubmittal loops.
- Name files for overlay comparison. Consistent, numerically sequenced filenames let reviewers compare your revised sheet against the prior version without hunting through the folder.
- Include a cover sheet checklist. List every required item on one page at the front of your plan set so the reviewer can confirm completeness at a glance.
- Keep a change log for resubmissions. A short summary of what changed since the last round saves the reviewer from re-reading the entire set to find your corrections.
- Export clean, reviewer-ready structural PDFs. Calculations formatted for print, not for internal use, cut down on clarification requests. Reviewing common structural drawing omissions before you submit catches gaps a reviewer would otherwise flag.
- Respond to prescreen comments inside ProjectDox, not through a side email. Keeping the conversation in the platform preserves the record reviewers actually check.
Pro Tip: Before you scale a PDF for printing or upload, double-check it against the original drawing scale. Scale errors when handling PDF drawings are an easy way to submit a plan sheet that measures wrong once a reviewer pulls out a scale ruler.
Why Organized Electronic Submittals Actually Change the Outcome
The city's checklist and file-naming rules aren't clerical hurdles. They're the mechanism that makes ProjectDox's overlay and versioning features work at all. Treat the checklist as the contract between you and the reviewer, not a suggestion, and your resubmittal cycles shrink accordingly.
The pattern holds across streamlined wood-frame permit submittals: applicants who front-load organization save far more time than they spend preparing it. A reviewer who can find every required item on the first pass moves your project forward instead of setting it aside for clarification.
— Evalin
A Faster Path to Permit-Ready Shear Wall Calculations
Getting your Bakersfield plan check submittal through prescreen on the first try depends on clean, complete structural documentation, and that's exactly where ShearWise Pro fits into your workflow. Instead of building shear wall calculations, hold-down forces, and story drift checks from scratch in a spreadsheet, ShearWise Pro organizes wall lines, openings, full-height segments, and transfer strap data into a report built for reviewer coordination on low-rise wood-framed projects.
Before you upload your next structural package, run your shear wall layout checks and export a clean PDF report designed to hold up under prescreen review. ShearWise Pro offers a Three-Report Trial at no cost, so you can test the report output on a live project before subscribing. Current prices are available on the pricing page. Sign up to try ShearWise and see how a reviewer-ready report changes your next resubmittal cycle.
Official Bakersfield Resources to Bookmark
Keep these pages on hand for every submittal:
- Development Center for contacts and general submittal guidance.
- Electronic Planning Application Submittal Process for checklists and step-by-step instructions.
- e-Permit and Plan Review Portal (ProjectDox) for account creation and uploads.
- California Building Code (CABC 2022) for the code basis behind plan review requirements.
Sources
- Development Center | Bakersfield, CA - Official Website
- City of Bakersfield e-Permit and Plan Review Portal
- Electronic Planning Application Submittal Process | Bakersfield, CA - Official Website
- Submittal Requirements Bulletin (example: small PV expedited submittal)
FAQ
Where Do I Submit a Bakersfield Plan Check Submittal?
Submit through the City of Bakersfield e-Permit and Plan Review Portal, built on ProjectDox, which handles most building, planning, fire, water, and public works applications online.
What Happens if My Permit Type Isn't in the Portal?
Contact the Development Center at DevBld@BakersfieldCity.us or 661-326-3720 to confirm the alternate submittal method, since some permit types are still being added to the electronic system.
Why Do Plan Sheets Need To Be Single-Sheet PDFs?
ProjectDox relies on single-sheet PDF uploads to overlay and version individual sheets; a multi-sheet PDF prevents staff from swapping one corrected page without a full resubmission.
How Long Does Plan Review Take in Bakersfield?
Timelines depend on complexity: a simple, qualifying small solar PV permit can review in 1 to 3 days, while standard residential plan checks with structural and MEP scope typically take longer.
Can ShearWise Pro Help With My Structural Submittal?
Yes. ShearWise Pro generates permit-ready shear wall calculations, hold-down forces, and clean PDF reports for 1 and 2-story wood-framed projects, and offers a free Three-Report Trial before any paid subscription.