Good coordination with a plan reviewer comes down to three habits: submit a complete package, tie every message to a specific revision, and answer each correction with a written response that shows where the fix is. Reviewers work from the documents you send, so the clearer and more organized those documents are, the fewer correction cycles you go through. For 1-story and 2-story wood-framed projects, the structural calculations are often where comments pile up. ShearWise Pro organizes shear wall calculations into clean PDF reports built for review coordination.
This guide is for engineers, architects, designers, drafters and builders submitting residential wood-frame work in California, Oregon, Nevada and Bakersfield. It explains what reviewers do, how to submit, how to answer corrections, and what to check locally.
TL;DR
- A plan reviewer checks your documents against the codes the jurisdiction has adopted. They do not design the project for you.
- Submit complete, legible, to-scale PDFs with a title block, code analysis and the engineer's calculations. Missing items cause delays.
- Answer every correction with a written response that points to the sheet or detail where the change is, and cloud each change.
- Confirm the plan revision with the reviewer in every message, and open returned PDFs to look for markups.
- Report shear wall calculations in an organized, repeatable format so the reviewer can follow wall lines, hold-downs and straps without hunting.
Table of Contents
- What a plan reviewer does, and what they do not do
- Submit a package the reviewer can actually review
- Keep every message tied to the right revision
- Respond to corrections so the reviewer can close them
- Shear wall comments: where structural coordination stalls
- What to check by jurisdiction
- Why a streamlined submittal shortens the conversation
- Prepare shear wall reports with ShearWise Pro
- Our view on working with reviewers
- FAQ
- Sources
What a plan reviewer does, and what they do not do
A plan reviewer, also called a plans examiner or plan checker, reads construction documents and decides whether the project meets the building codes the jurisdiction has adopted. The ICC's Building Plans Examiner exam outline describes the job as verifying complete plans and specifications, the design calculations that support structural designs, and the other items the permit depends on. The checks run from setbacks and occupancy classification to construction type, height and area, accessibility and materials.
In California, the California Building Officials job overview adds two duties that matter to you as an applicant: the examiner communicates corrections and requirements to applicants, and gives guidance on code and state-mandated requirements.
There is a boundary on that guidance. ICC training material describes reviewers as ambassadors, educators, facilitators and decision-makers, and says their responsibility to the community does not allow direct involvement in design because of liability. In practice, a reviewer will tell you what the code requires and where your documents fall short. They will not choose your hold-down, re-lay your wall lines or redesign your openings. That work stays with the engineer or designer of record.
The same reviewer is looking at much more than structure. Accessibility, for example, is on the checklist, and site elements such as ADA compliance for commercial paving are a reminder of how many disciplines a permit set touches. Your job is to make the structural portion easy to find and easy to verify.

Submit a package the reviewer can actually review
The cheapest correction cycle is the one you never trigger. The ICC's Permit Tech Study Companion notes that the building official needs the construction documents to determine code compliance, and that an incomplete submittal means reviewers cannot complete their tasks, which causes delays.
Oregon's Building Codes Division publishes one of the clearest lists of what "complete" means in its Plan Review Guide. Even if you work in California or Nevada, it is a useful baseline:
- Plans that are complete, accurate, legible and drawn to scale, never labeled "preliminary" or "not for construction."
- A completed application form for each discipline.
- Zoning, DEQ and sanitation approvals where they apply.
- Engineer calculations.
- A title block with address, parcel number, owner, preparer contact, date, scale and sheet index.
- A 3-by-3-inch blank space for reviewer stamps.
- A code analysis sheet that establishes the occupancy classification early.
The same guide lists common causes of delay: not coordinating with every authority having jurisdiction (the agency that enforces a given code or approval), missing land-use approvals, and drawings that are not final. It also says electronic plans must be PDFs, because firewalls block unsupported file types.
File size is a quiet cause of failed uploads. If your portal limits uploads, split the set by trade and keep each file within the limit, as we explain in keeping each trade PDF under 50 MB. For a deeper look at what goes in the package, see our notes on what U.S. reviewers require in structural calculations.
A pre-submittal checklist for wood-frame projects
- Confirm the adopted code edition with the building department before you finalize calculations.
- Check that every sheet carries the same revision date and the sheet index matches the set.
- Confirm the structural calculations reference the same wall lines, openings and roof information shown on the plans.
- Confirm hold-down and strap callouts on the plans match the calculation output.
- Combine or split PDFs to meet the portal's file rules.
- Contact the other agencies involved before you submit, not after the first hold notice.
One missing sheet can send a resubmittal back to the start. Our article on the permit resubmittal package covers how to assemble it so that does not happen.
Keep every message tied to the right revision
Most coordination mistakes are version mistakes: the reviewer is looking at one set, the engineer is answering from another. Three habits prevent it.

Name the revision in every message. Use a revision identifier or date in the subject line and the first sentence. Oregon asks for a filename format such as plans_mm-dd-yy.pdf and an updated title-block date, according to the Plan Review Guide. That convention works anywhere.
Open the returned files. Las Vegas's Managing Projects During Reviews guide tells applicants to check the portal for access to submitted PDFs, to open documents because markups are sometimes placed on the files during review, and to check the assigned plan reviewer under Check Status, which it calls critical to understanding review status. A comment placed directly on a sheet can be missed if you only read the correction letter.
Route the resubmittal to the right person. Henderson, Nevada, requires a Re-submittal and Revision Submittal Form with resubmittals, corrections or revisions so they reach the correct department or reviewer. Revisions also go in with a written narrative of the changes.
If a reviewer's comment is unclear, ask a direct, narrow question about the code section or the sheet. Ask what the comment requires, not how to design around it. That keeps you on the right side of the design boundary described above.
Respond to corrections so the reviewer can close them
After each review cycle, the plans examiner either approves the plans in their current form or issues a hold notice or correction notice, as Oregon's guide and Sacramento's Electronic Plan Check guide both describe. The ICC's plan review presentation describes the loop the same way: the applicant receives a report, makes corrections, resubmits, and the permit issues once the plans are approved.
What the reviewer expects back is consistent across these jurisdictions:
| Requirement | Oregon BCD | Sacramento (CA) | Henderson (NV) |
|---|---|---|---|
| Written response to comments | Yes, listing resubmittal documents and where each item is found | Yes, revised plans must be accompanied by a response | Written narrative of changes |
| Changes marked on the plans | Clouded, same format and scale | Clouded and delta'd | Revision form routes changes to the right reviewer |
| Version control | Date-stamped filename and updated title block | Not stated in the guide | Not stated in the guide |
| Engineered plans | Changes by the engineer of record or with a release letter | Not stated in the guide | Not stated in the guide |
A response letter that works follows the reviewer's numbering. For each comment, restate it briefly, state what you changed, and give the sheet, detail or page number. Oregon requires exactly that: the letter must detail the resubmittal documents and show where the requested information is found.
Write the response like a checklist
- Number each answer to match the reviewer's comment.
- Cite the sheet and detail, for example "S2.1, Detail 4," not "see plans."
- State what changed and what did not. If you disagree with a comment, cite the code section and explain.
- Cloud every change and update the revision date.
- Do not change anything else without saying so. Unflagged changes are the fastest way to open new comments.
Two cautions apply. First, in Portland, all review groups must complete their review before you can submit corrections, so do not expect to resubmit partial answers early. Second, California's Division of the State Architect, which reviews public school and similar projects, has a stricter model: under PR 24-01, any alteration or addition by the design team during the first phase of back check halts the back check, and it is rescheduled no sooner than two weeks later. Most residential work does not go through DSA, but it shows how costly unannounced changes can be.
Shear wall comments: where structural coordination stalls
For wood-frame work, the comments that come back most often are about the lateral system: whether wall lines are identified, whether full-height segments and openings are handled consistently, whether hold-down forces and transfer straps are called out on the plans, and whether the calculations and drawings agree. Reviewers read these against the plans, so the calculation report should follow the same wall line labels and sheet references the drawings use.
Three practices help:
- Use the same wall line names everywhere. If the plan says "WL-A" and the report says "Line 1," the reviewer has to translate.
- Show the load path completely. Roof information, wall segments, hold-down forces and transfer straps should read in sequence, and for two-story buildings the story drift check should be included.
- Keep the as-built record. If walls change in the field, reviewers expect a record. Our article on shear wall as-built changes covers the three records to keep.
For the specific comments you are likely to see and how to clear them, read 3 moves to clear shear wall plan check comments and the four reviewer nonnegotiables with a sample report. In California, also check the list of common structural drawing omissions and, for additions, the two-story addition design guide.
What to check by jurisdiction
Procedures differ by city and state, and they change. Treat the notes below as a starting point and confirm the current rules on the department's own page before you submit.
California and Bakersfield
California jurisdictions work from the California Building Code, which is updated on a cycle, and each city adopts it with local amendments. At its November 5, 2025 meeting, the Bakersfield City Council took first reading of ordinances amending several Municipal Code chapters relating to the 2025 California Building and Construction Codes. Confirm with the Building Department which code edition applies to your submittal date.
Cost is also part of coordination. Bakersfield's proposed 2024-25 master fee schedule lists residential expedited plan review at $94 per hour with an 8-hour minimum, and a separate Additional Plan Review fee for changes, additions or revisions to approved plans. Fees are revised periodically, so check the current schedule. The practical point is that a clean first submittal and complete revisions cost less than rework after approval. Our guide to Bakersfield plan check submittal rules walks through what to prepare.
Oregon
Oregon's Building Codes Division accepts plans through its E-permitting system, by email or in person. Its guide recommends contacting all authorities having jurisdiction beforehand and adding a written narrative explaining design goals and how project challenges are addressed. Many Oregon cities and counties run their own programs, so confirm who reviews your site.
Nevada
Las Vegas and Henderson both run portal-based review. Check the assigned reviewer, open the PDFs for markups, and use the resubmittal form and narrative Henderson requires. Other Nevada jurisdictions have their own forms, so look for the equivalent before you upload.
Why a streamlined submittal shortens the conversation
Every reviewer question you can answer before they ask it is a cycle you save. A package with a code analysis, a clear sheet index, matching revisions and calculations that follow the plan's labels lets the reviewer move straight to judgment calls. Our article on the benefits of streamlined plan review submittals lays out how that plays out on wood-frame permits.
Prepare shear wall reports with ShearWise Pro
ShearWise Pro is an online shear wall calculator and report platform for 1-story and 2-story wood-framed buildings. It helps you organize wall lines, openings, full-height segments, hold-down forces, transfer straps, roof information and story drift checks, then export a clean PDF report for permit and review coordination. It is built for the residential 1- and 2-story workflow rather than as general-purpose structural software.
The Three-Report Trial costs $0 and includes three watermarked reports, so you can run a real project through the workflow. After that, Professional Monthly is $29 per month and Professional Annual is $250 per year. You can also view the sample calculations or sign up to try ShearWise.
If you want a closer look at the product first, see shear wall software for residential wood buildings.
Our view on working with reviewers
We think of the plan reviewer as the person who has to be able to follow your logic in one pass. They cannot redesign the project and they should not have to reconstruct it. When a shear wall report uses the same wall lines as the drawings, shows the openings and full-height segments, and carries the hold-down forces and transfer straps through to the plans, the conversation gets shorter.
That is why ShearWise Pro is focused on 1-story and 2-story wood-framed buildings. The platform is built to organize the calculations a residential reviewer looks for and to produce a clean PDF report for review coordination, with project organization and fast report generation that fit how engineers, designers and builders actually work.
Coordination is a habit, not a favor. Name the revision, cloud the change, point to the sheet. When the structural report is already in order, you can spend your time on those habits instead of rebuilding calculations after a comment.
Evalin
FAQ
What is a plan reviewer?
A plan reviewer, or plans examiner, is the jurisdiction's staff member who checks construction documents against the adopted building codes before a permit is issued. They also communicate corrections to the applicant and give guidance on code requirements. They do not take part in the design.
Can I call the plan reviewer to talk through a correction?
Yes, in most jurisdictions you can, and it often helps. Keep the question about what the comment requires or which code section applies. Follow up in writing and cite the revision, so the record shows what was agreed and which set it applies to.
What should a response letter to plan check comments include?
Answer each comment by its number, state what changed, and give the sheet, detail or page where the change is. Cloud the changes on the plans and update the revision date. Oregon's guide requires this kind of letter, and Sacramento and Henderson ask for a response or narrative with revised plans.
How many correction cycles should I expect?
It varies by jurisdiction, project and how complete the first submittal was. Resubmitted plans generally take less processing time than the first review, according to Oregon's guide. Check the department's current review-time information, since staffing and workload change.
Does ShearWise Pro replace the engineer of record?
No. ShearWise Pro is a calculator and report platform for professionals, who remain responsible for their designs. It organizes the shear wall calculations and produces a clean PDF report that supports your review coordination.
Sources
- ICC Building Plans Examiner exam outline (B3)
- California Building Officials plans examiner job overview
- ICC 2021 IBC plan review presentation
- ICC 2024 Permit Tech Study Companion
- Oregon Building Codes Division Plan Review Guide
- Las Vegas: Managing Projects During Reviews
- City of Henderson building permit guidance
- City of Sacramento Electronic Plan Check submittal guide
- Portland PPD checksheets
- California DSA PR 24-01: Back Check for Design Professionals
- Bakersfield City Council Meeting 515, November 5, 2025
- City of Bakersfield proposed master fee schedule for 2024-25
- ADA compliance for commercial paving